Three weeks since the last update, we now have mains water connected
and doors, windows and radiators fitted into the cottage.   The main house
has had all wooden beams sandblasted and doors into the upper
bathrooms have been relocated for improved access.
The cottage with new doors and windows.
Mains water flows into Mazzaforte, 29 September 2007.
New
radiators in
the cottage.
The brick arch linking the living
room with the dining room has
also been sandblasted.
The ceiling beams in the living room,
freshly sandblasted.
The plumbing for the bathrooms and central heating on the top floor is
nearly complete.  On the first floor, the stone base for the fireplace has A
very productive week, with a lot of progress made on the main house.  
been rebuilt and the old damaged tiles on the floor of the loggia have been
removed.  On the ground floor - in the dining room, the brick arches have
been prepared for re-pointing and plastering of the walls will begin this
coming week.  Outside, a new paved surface to the courtyard area to the
west of the entrance bridge is being laid.  
Paving
delivered by
digger
The trench running down the drive from the
new meter house to the cisterna has been
filled in.  We have also now decided to leave
the drive entrance where it is - instead of
moving it further down the road and in
through the laurel hedge.  This means the
car park will be confined to the area on the
right of the drive - which you can see in the
photograph to the left.
Drains and reinforcing steel
being laid in the courtyard.
The stone base for the fireplace
in the reception room on the
first floor re-assembled and
cemented in place.
Half of the
area paved
by close of
play on
Saturday.
Concrete poured and levelled.
Click on any
image for an
enlarged view.
Underfloor pipework for
the central heating on
the second floor snakes
its way across the
bedroom floor.
New sink and tiling in the
second bathroom in the
cottage.
The external stairs
leading up to the
loggia are being
resurfaced in
travertina.
The cut
travertina
treads were
delivered this
week.
Building Project Update - 14 October 2007
Building Project Update - 7 October 2007