This has been an absolutely critical week, with some major tasks
completed. All pipework for the plumbing and the tubing for the electrical
wiring has been laid on the two lower floors of the main house and
concreted over. This is now dry which means the underfloor heating can
be laid on top, commencing Monday. The kitchen has not yet been done,
because there is some additional electrical wiring still to be installed.
The kitchen has been installed in the cottage and most of the lights fitted.
final coat of paint, wood floor laid on the first floor, pianelli cleaned and
polished on the ground floor and internal doors fitted.
Concreting almost complete. A good view of the cantilevered stone staircase which
is a major feature in the reception room.
The conduits for the electrical wiring
(black) and the water pipes (white)
leading to the bathrooms laid across
the floor of the main reception room.
The cantina floor, mid-week.
|
Kitchen.
Sitting room.
11.00 - Travertina surfaces in place.
|
12.00.
10.00 - first units unpacked and
put into position.
Two days later, the concrete goes down.
|
Having the kitchen installed in the cottage was a milestone event. The
Carlini team completed the job in one day - and it looks terrific.
Cistern for the loo and pipework for the boilers beneath the loggia stairs.
|
The cantina floor by Saturday evening. The dining room (left) and the
sitting room (right), fully concreted.
Building Project Update - 18 November 2007